November 27, 2020

Download Excel Data

 

 

 

 

 

 

 

 

 

 

 

 

 

  • Ontario plans to refurbish 8,000 MW of nuclear capacity at the Bruce and Darlington sites during 2016–2032 time period.
  • Pickering site will remain in service until 2024, after which 3,000 MW will be taken out of service.
  • Natural Gas is expected to backstop Nuclear during refurbishment.
Map of the Region

 

 

 

 

 

 

 

 

 

 

 

This shows Ontario nuclear power stations (Bruce, Pickering, and Darlington) along with major natural gas pipelines and hubs.